Issue 12 - January 3,
2010
In this issue:
-
The series by Aaron
Shenhar, Unleashing the Power of Project
Management, wraps up with the last article: "Part 4 - The New
Adaptive Project Management Framework".
-
Following that
is the third article in a series on "Common Barriers to Successful Projects" by me, Ray
Posch.
PM Insights See PM Insights, our new blog for conversations and shared insights about project management.
http://www.pminsights.com/
Authors Welcome If you are an experienced project manager
and would like to write articles for the newsletter, please email me at ray@projectsuccesstips.com. We are looking for first-person project stories with real take-away
insights.
Unleashing the Power of Project Management
Part 4 - The New Adaptive Project Management
Framework By Dr. Aaron J.
Shenhar
Based on our research we suggest changing the paradigm of project management and accepting
things as they are. The new framework is success-focused, flexible, and adaptive, and we can simply call it the
“Adaptive Project Management Model;” it differs from the traditional approach in several ways, as shown in Table
1.
Table 1: From Traditional to Adaptive
Project Management
|
Model
|
Traditional Project
Management
|
Adaptive Project
Management
|
|
Project goal
|
Getting the job done – on time, budget, and
requirements
|
Getting business results – meeting multiple
criteria
|
|
Project Plan
|
A collection of activities that need to be executed as
planned to meet the triple constraint
|
An organization and a process to achieve the expected
goals and business results
|
|
Planning
|
Plan once at project
initiation
|
Plan at outset and re-plan when
needed
|
|
Managerial Approach
|
Rigid, focused on initial
plan
|
Flexible, changing,
adaptive
|
|
Project Work
|
Predictable, certain, linear,
simple
|
Unpredictable, uncertain, non-linear,
complex
|
|
Environment Effect
|
Minimal, detached, once the project was
launched
|
Affects the project throughout its
execution
|
|
Project Control
|
Identify deviations from plan and put things back on
track
|
Identify changes in the environment and adjust the plans
accordingly
|
|
Distinction
|
All projects are the same
|
Projects differ
|
|
Management style
|
One size fits all
|
Adaptive approach – one size
does not fit all
|
According to this model projects are not just a collection of activities
that need to be completed on time. Projects are business-related processes that must deliver business results.
They are not predictable or certain. Rather, they involve a great deal of uncertainty and complexity, and they
must be managed in a flexible and adaptive way. Planning is not rigid, fixed, or done once and for all; instead,
it is adjustable and changing, and as the project moves forward, re-planning is often appropriate or even
unavoidable. Project management styles must adapt to the specific project and its requirements, and one size
does not fit all.
While this approach represents a shift in thinking, it is inevitable to meet today’s organizational challenges.
While no framework could provide all the answers, we believe that every organization can significantly improve
its business results and achieve more homeruns from its projects if it will consciously apply the adaptive
project management frameworks.
One final word: We do not suggest, however, eliminating the traditional
approach. Rather, we are building on it. Many elements of traditional project management continue to be useful; yet, the
overall approach will be augmented. As established by the conventional approach, each project must have a work
breakdown structure, a schedule, a budget, an organization and a process. All those are necessary building
blocks for well-organized successful projects. These building blocks will only form the baseline to leading the
project in a flexible way. Not only do projects have to monitor and review their progress, they must
periodically examine the need for the product and the customer’s position. Are the initial assumptions still
valid? And if not, what adjustment does the project have to make in order to guarantee better success.
Furthermore, in many projects it is impossible to build a clear and detailed plan. The uncertainty involved is
simply too high to enable creating a clear project plan with all its bells and whistles. Instead, companies must
initiate pilot programs, namely, small-scale efforts that will help remove some of the unknowns before the
company can commit to the major large effort. In other situations, managers must create product prototypes that
will be tested by customers before the final product requirements are set and
determined.
In sum modern projects involve a great deal of
uncertainty and complexity, as well as other constraints such as time, political pressures, economical risks,
and many others. Each project is unique and it has to be managed it its own way that best fits it unique
characteristics, risk and complexity. Only after companies learn how to manage projects in an adaptive and
flexible way, will projects become the powerful competitive assets that they can be.
Dr. Aaron J. Shenhar is a Professor of Project and Program Management
at Rutgers Business School and the CEO of the Technological Leadership Institute, a consulting and training company
in technology and project leadership— http://www.tli-llc.com/. He is the coauthor of Reinventing Project
Management: The Diamond Approach to Successful Growth and Innovation, Harvard Business School
Press.
Common
Barriers to Successful Projects - #15-21 By Raymond
Posch
In this series, I am writing briefly about some barriers
to project success that
are fairly common in my experience. Here
are the next seven in my list:
- Not
getting team commitment to the plan – When the plan is developed with team
involvement, they will naturally be bought in. But by asking them to commit to the plan, they will more
likely point out where they have doubts about or problems with the plan. When the team resolves those
issues and commits individually and collectively to the plan, probability of success quadruples. Believe
me.
- Not
involving sponsor and stakeholders in the planning process – The sponsor or customer
representative needs to be heavily involved in the planning process because the business/customer
organization will be the users of the results and should best understand what is needed. Stakeholders also
have some vested interest in the project or the results (since that is the definition of “stakeholder”).
Therefore, they need to be involved in the planning process also, but it may be at the beginning and at
selected points rather than throughout.
- Not
leveraging the team throughout the project – The power and synergy of the team
can be tapped throughout the project, not just during planning. Keep them informed about the external
aspects of the project anything that might impact the project. Remind them of the business goals and
expected results for the business/customer. Discuss risks and mitigation plans on a regular basis. The team
will provide inputs, ideas, and solutions far more effective that you, the PM, could come up with on your
own.
- PM
not removing obstacles to the team in getting their work done – One of the jobs of the project
manager is to facilitate the team in every phase of the project. If something is negatively impacting the
progress of the team, the PM must identify that something and eliminate or minimize its negative impact, if
possible. One of the big problems today is excessive multi-tasking – project specialists being assigned to
work on too many projects at the same time. Negotiation with the resource managers on behalf of your
project comes with the territory, but the ideal – getting bigger chunks of the specialists’ time is not
always doable. This can be one of those things that needs to be escalated up the management
chain.
- Poor
communication with sponsor and stakeholders – The PM needs to learn about the
sponsor’s and stakeholders’ requirements, concerns, and interests in the project. One-on-one discussions,
with the PM doing a lot of listening, is often the better way to do that than in group meetings. It is also
a good way for the PM to build relationships with these individuals based on direct interaction and
learning about the people, their business roles, and what they think (or feel) is most important to them
relative to the project.
- Inadequate team
resources – If the project manager cannot
arrange with resource (i.e., team or department) managers to have the right number of people with required
skills for the necessary level (%) of effort when needed, then obviously the planned schedule will not be
achieved. This is a common problem in many cases, especially when too few people are being asked to support
too many projects.
- Pulling resources off for “higher
priorities” – One of the most frustrating
situations for PMs is to think that they have people with the right skills and right personality fit
committed to the project on a planned schedule, or even working on project tasks, only to have them pulled
off to work on some higher-priority project. This is deadly, because even if there is someone else with
equivalent skills available, they may not be as familiar or up-to-speed on the project, or they may not be
as good a fit with the team, and the net result may be that much greater time and PM attention may be
required to get the planned tasks completed.
Raymond Posch is publisher of Weekly PM
Insights newsletter as well as being a full time project manager. See Ray's bio on our Meet the Experts page. He can be
reached at ray@projectsuccesstips.com.
Issue 13 - January 10,
2010
In this issue:
-
Glen Alleman discusses risk management frameworks
in the third article of his series on programmatic risk management. (We didn't come up with a
snazzy title, like I suggested we should, but Glen has included some sexy diagrams that are worth
studying.)
-
We take a look at more
barriers to project success in the last article of a series by me on common problems to avoid.
Those issues that are organizational in nature, of course, are somewhat out the PM's control - but
maybe you have an executive sponsor who can help.
-
Elizabeth Harrin examines the results of a survey on
PMO effectiveness. If you're in a larger organization that has a PMO, I hope it's a good one. (The best
PMOs, in my opinion, focus on making projects successful rather than on enforcing a bureaucratic
process.)
By the way, Happy
2010! I hope you have a great year.
Authors Welcome If you are an experienced project manager
and would like to write articles for the newsletter, please email me at ray@projectsuccesstips.com. We are looking for first-person project stories with real take-away
insights.
Risk
Management Frameworks
Part 3 in a Series on Programmatic Risk
Management By Glen
Alleman
Let’s start with a quick review of the previous two articles in this series on Programmatic
Risk Management. This article will establish the principles of Risk Management, ending with one of the top level
approaches to communicating about risk status.
Programmatic risk arises from three sources: (1) the naturally occurring “noise” in the cost
and schedule. This is called the Deming risk. Attempts to control this type of risk is a waste. (2) The
variances that emerge dynamically through the interactions of the work elements of the schedule, the cost
components, and of course the performance of the technology. This is a stochastic risk driven by the underlying
probabilistic activities of the planned work. (3) The technical risk causing unplanned delays and cost
overruns.
Managing all three of these risk types calls for a structured approach. There are many
suggestions for managing risk. Some are actually credible. Let’s start with a framework for managing risk that
is a guide for assessing the success of any specific risk management approach.
There are two primary frameworks:
1. The Software Engineering Institute’s
Continuous Risk Management,
http://www.sei.cmu.edu/solutions/risk/. Start with the tutorial titled Rethinking
Risk Management: NDIA Systems Engineering Conference.
http://www.sei.cmu.edu/library/abstracts/risk/upload/dorofeetutorialndia09_8819.pdf
2. The US Department of Defense Risk Management
Process,
http://www.acq.osd.mil/sse/docs/2006RMGuide4Aug06finalversion.pdf
Both frameworks take care to separate Issues from Risks. Risk management is the overarching
process that encompasses identification, analysis, mitigation planning, mitigation implementation, and
tracking.
An important difference between issue management and risk management is that issue management
applies resources to address and resolve current issues or problems, while risk management applies resources to
mitigate future potential root causes and their consequences.
The Software Engineering Institute’s CRM has the following structure:

While the US DoD Risk Management process has the following
structure:
Both have similar elements and both have been field proven in a variety of domains. The SEI
paradigm is centered on software development, while the DoD paradigm has a more general purpose
approach.
Both these paradigms appear to be complex and overbearing in many project environments. But it
turns out the failure of risk management is high in many commercial IT environments because of these missing
frameworks. You can pick one of the other, but you need to pick one.
So Using One of These Risk Management Paradigms, How Can You
Take the First Steps?
Managing programmatic and technical risk involves more than making lists and checking them
twice, it means actively “mitigating” risks with the same project management processes used to deliver the
project:
-
Risk is the possibility of suffering a
loss
-
Risk management provides the mitigations to address the
possibility of suffering a loss
-
A risk adjusted plan identifies risks (probability of
occurrence) and mitigations (cost and duration) that maintain the cost and schedule
baseline
Let’s start with some core project failure modes:
-
The defined project deliverables are not feasible given
the time, cost and technical measures
-
The project deliverables are feasible, but their timing
and resource objectives are inadequate for delivery
-
The project deliverables are poorly planned and behave in
chaotic ways for cost, schedule and technical measures
Let’s look at the four standard approaches to “handling” the risks. Identifying, analyzing,
planning, and monitoring are important as well. But let’s start with the end in mind – how do we handle the
risk?
-
Avoid: alter the approach to the problem and bypass that
path in the project network.
-
Transfer: assign the risk to team that can mitigate the
risk
-
Assume: assume the risk with no further action other than
to watch for a change.
-
Mitigate: the risk by executing the tasks needed to reduce its likelihood
and any consequences from its outcome.
Before ending this article, let’s look at the next most important activity. “Communicating”
the reduction of risk. One powerful approach is to show physically how the risk is being reduced with the
passage of time. This is a sample from the Active Risk Manager (ARM) tool.

The key here is to show not only the starting status of the risk, in this case RED, but to show explicitly when the
risk will be reduced. With this approach, risk management follows the Tim Lister advice:
Risk Management is
How Adults Manage Projects
The next article will show you how to
perform the other activities in risk management and construct the picture above in simple Excel spread sheet
extracted from Microsoft Project.
This
article is part of a series by Glen on risk management. See Glen's bio
on the Meet the Experts page. He can be reached at Lewis &
Fowler or at his
blog, Herding Cats.
Common Barriers to
Successful Projects - #22-27 By Raymond
Posch
In this series, I am writing briefly about some barriers
to project success that
are fairly common in my experience. Here
is the last set in my list:
- Lack
of resource management in the organization – Of course there is some kind of
“resource management” in place, but if the organization has not stepped up to managing specialized people
resources in effective ways for competing projects, there will be many issues like several mentioned in
this list.
- Not
identifying and managing risks – All large and complex projects have
risks which must be taken into account. Risks are known (identified) or unknown (unidentified) events that
can have an impact. (They are usually negative impacts, although positive events/impacts can happen too,
and they’re called opportunities.) Consideration must be given in the planning process to the events that
are most likely to occur and/or that would have the largest impact. For those, the team should spend some
time, based on probability of occurrence, of how to deal with the risk either beforehand or when the event
occurs. Some of these risks, if appropriate, might justify bringing in some people (executives or
specialists) from outside the core team to make recommendations.
- Uncontrolled scope
creep –
This one is a classic, but it is a true and common problem. There is often a tendency of the requesters of
projects – the customers, or possibly more often, the users of the product being developed – to realize
during development that there are other features that should be added. The features might be absolute
necessities, or they might be nice to have. But allowing more features to be added almost always expands
the work, the schedule, and the cost.
- Not
informing management promptly when help is needed – If the project runs into problems
that will definitely or potentially put it behind schedule and over budget by a significant amount, or at
risk of not meeting the goals, then the PM must bring the matter to management attention. This is
especially true, if the PM does not quickly identify a solution that can bring the project back “on track”,
because then escalation and requests for help may be required, depending on exact circumstances. Failure to
inform management (or the PMO if it is a point of control) that there is a problem is a serious mistake.
Senior management needs to know when any important project is in trouble.
- Lack
of management response when help is requested – Just as serious, is the case where a
project manager informs management that a project is in trouble and nothing is done. At the very least,
there should be a meeting (or review) to determine 1) if the PM has correctly explored the options, and 2)
whether any other solutions are possible from a higher, cross-project perspective. Of course, there are
situations where the project in trouble is the lowest priority, or the factors involved are outside of the
organization’s immediate control. But in any case, the PM should be given advice on how to
proceed.
- No
monitoring (project reviews) and control outside of team – Monitoring and control means
checking whether the project is staying reasonably “on plan”, and taking steps to adjust if necessary. It
should be done at two levels: by the project manager and team, and by someone with appropriate authority
outside of the team – usually executive management or a PMO (if one exists). Large complex projects should
typically have formal outside reviews scheduled at certain key points in the project
timeline.
The full list of 27 barriers to success outlines a number of things that can negatively impact projects,
resulting in schedule and budget overruns and potentially not achieving the expected or desired business value. So,
studying these barriers to success may help you avoid the potential problems. Again, not all of the identified
problems are controllable by the project manager, but the large majority of them are. The project manager must step
up to the challenge.
Raymond Posch is publisher of Weekly PM
Insights newsletter as well as being a full time project manager. See Ray's bio on our Meet the Experts page. He can be
reached at ray@projectsuccesstips.com.
How good is your
PMO? By Elizabeth
Harrin
A new study has shown that nearly half of Project, Programme and Portfolio Management
Offices (PMOs) rate themselves as Fair or Poor in terms of effectiveness. I think that’s terrible, especially as
it was the PMO team or those close to them who responded to the survey. As the purpose of having a PMO is to
make an organisation more effective there can’t be much job satisfaction for those
people.
The study identifies the main objective of a PMO as:
to provide a group dedicated to supporting and integrating operations across organizational boundaries. This
is accomplished by providing services that either mitigate or directly address the root cause of the challenges
being faced.
The main challenge identified in the study is the perennial problem of departmental silos. This is less of an
issue if your PMO just serves one department (and only 26% of them claim to be enterprise-wide). However, say your
PMO is one of the 36% just supporting IT. How many projects does IT do that only impact IT? The PMO will still need
to work with internal customers to gather data for reports and dashboards – reporting and dashboards being one of
the biggest things that PMOs do.
Churning out good reports is not one of the things that makes a PMO effective. The factors highlighted in the
research that correlated with being an effective PMO were:
- Having a high level of process maturity.
- Reporting to C-level executives, with teams reporting to the CEO being the most effective.
- Having between four and six dedicated staff, although further analysis shows that more staff equals more
effectiveness. The researchers don’t correlate this with staff numbers though. The highly effective PMOs from
the study have over 15 staff but if their organisation is only made up of 20 people you would not be able to
say this was an effective team in business terms.
- Being around a long time. The most effective PMOs have been in existence over four years, and the survey
participants said that the PMO started to be properly effective after three years. That’s a long time to wait
for business benefit. I don’t think that they meant that for the first two years the PMO team are pointless,
but it does take a while to bed in the new way of working that a PMO brings.
It’s difficult to influence many of these. If you are a project manager working for a PMO you won’t be able to
change your line management structure. If you report into a business unit VP you are doomed to be an ineffective
team forever more. You can’t change how long the PMO has existed, you just have to sit it out until three years
have passed and people can no longer imagine how they ever got by without you. Having said that, there are some
things you can do in the meantime to bump up your effectiveness levels.
Terry Doerscher, Chief Process Architect for Planview who commissioned the study, has the
following recommendations:
- Benchmark your PMO: compare it to others in your sector. This is a huge task if you want to do it properly
and assess the maturity levels of business processes and work out where the biggest operational challenges
are.
- Assess the performance of your PMO: again, a big undertaking as it means working out where processes are
performing poorly and putting that right.
- Make sure everyone knows what the PMO is: Doerscher recommends ensuring that the PMO has objectives and
that its role within the organisation is clearly defined – and communicated.
- Ensure the PMO can meet those objectives: you need a large enough team to be able to deliver everything you
set out to achieve.
- Get your PMO executive sponsorship: you can do this even without changing reporting lines, if you can find
an exec who believes in the PMO concept. If you do a great job for him or her they will spread the word among
their colleagues. Guerrilla PMO!
- And finally, don’t get bogged down in day-to-day admin. Instead spend time doing fabulous work on business
strategy.
Unfortunately, these kinds of initiatives are likely the be among the first to suffer in the current economic
climate. I think PMOs do add value, but these recommendations all appear to be navel gazing in a time where more
focus is on delivering results with less than on benchmarking support functions. I’m not saying that you shouldn’t
do this, but not everyone thinks like me and this year I think PMO-improvement projects are going to be a casualty
of the credit crunch.
Nice study, shame about the operational realities, but if you can fit in supporting the development of your PMO
around delivering what the business is shouting for, then all credit to you.
Elizabeth Harrin, BA, MA, MBCS, is the author of the book "Project Management in the Real
World", writes the irreverent blog A Girl's Guide to Project
Management, and is a columnist for pmtips.net. (This article was previously published on her blog.)
See Elizabeth's complete bio on the Meet
the Experts page.
January 17,
2010
As you can see, I've been busy with some changes... Our new name is Project
Success Tips -- both the website and newsletter -- and we are making other changes.
Please see the explanation on the new website home page. The changes will be unfolding over the
next several weeks. I certainly hope you like them.
I posted a great new article on the home page. Sarah Gilbert offers some good advice (project success tips) from her own project
experience.
Project Success Tip of the
Week
These days, it has become critical that every project that consumes any significant amount of
resources must 1) be fully aligned with business strategy and goals, and 2) must deliver the desired business
results. I will write more on this later - but for now, this should be near the top of your list of project
management success principles.
Align with the
Business
At project initiation, be sure you fully understand the project's business goals and the
value to be created for the business. Ensure that the project and its goals are aligned with the current
business strategy and priorities, then communicate the business goals to the team throughout the
project.
To your project success!
Cheers,
Ray
January 24, 2010
Greetings {firstname}!
Sometimes projects go wrong from the start, and the best course of action is to
promptly stop the project, figure out what went wrong, and restart... It happened to me.
Restarting a
Project By Raymond
Posch
This is a story about having to stop a
project gone wrong, examine the team dynamics and project approach that was not working, and then restart
the project with a major replan of team organization, work effort, and timeline. (This story also has
some useful lessons learned that are applicable to process improvement projects generally with a
successful methodology.)
The Context
When I was the PMO manager of a dot.com
startup, I was asked to lead a project to "achieve CMM level 3 in the shortest time possible". This was
for a subsidiary of Perot Systems that was developing advanced ecommerce systems. It was during those
exciting times of the dot.com boom.
The business reason for wanting to get to CMM
Level 3 was that our best competitors were advertising CMM Level 3 certification. Our management team
thought that having the credential would allow us to prove ourselves more easily and compete in a highly
competitive marketplace.
At the time we were still learning what worked
and what didn't ...
Read the full
article
Project Success Tip of the
Week
Don't Just Manage,
Lead
Throughout the project, practice project leadership as well as project management.
Understand and promote the business goals of the project, and build and maintain strong relationships with
the team and customer.
Projects today require that a project manager demonstrate
project leadership capabilities in addition to management skills. He or she must fully understand and promote
the business context of the project: what the business goals are and why, what the customer organization
does, and what benefits the solution (project results) will bring the customer organization. The
project manager must also get to know the business sponsor, the team, and the stakeholders, become familiar
with them as people, and understand their needs and concerns for the project.
To your project success!
Ray
January 31,
2010
See my new blog post on "Project Management
Maturity in IT". It was based on my observations that many IT organizations do not consider managing
costs, especially labor costs, do be a necessary part of project management. And I offer my analysis of
why that is.
Not managing project costs is, in my opinion, an indicator
that the organization is still at a low level of project management maturity. Glen Alleman, on
his Herding Cats blog, has made that same point.
Read the full blog article
Project Success Tip of the
Week
Manage the Trade-offs
During the project planning process, manage the trade-offs between the project
constraints - especially scope, quality, schedule, and cost.
The triple constraints of scope, schedule, and cost are famous in the profession of
project management. (Quality can be added to the list, but it is effectively an aspect of the
product - i.e., the scope.) But they must be actively managed in negotiation with the customer or
sponsor. As illustrated by the so-called "triple constraints triangle", increasing the scope
naturally increases the schedule and cost. To decrease schedule or cost, the scope must be
decreased. The project manager must explain this fact of reality and not give in to the customer's
wishful thinking that they can increase the amount of work to be done without paying a
price.
|